Locate the failed neutral connection on the actual circuit drawing. A load-neutral interruption changes the load return circuit; loss of the source-neutral bond changes the grounding reference and ground-fault return path. Build the fault study from the remaining connections.

Draw the actual grounding nodes
Identify the winding neutral, load neutral, protective network, grounding electrode system and any intentional grounding impedance. Mark their actual connections in the represented operating state. Include other transformer or source grounding paths that may remain connected after the suspected failure. [1]
Do not convert every labelled earth into one ideal node if location or impedance matters. Equally, do not omit a physical connection because it is outside the main one-line diagram. These choices can manufacture or remove a return path in the model.
| Connection state | Path question | Evidence to reassess |
|---|---|---|
| Load neutral intact, source bond absent | Which path references the system to ground? | Phase-to-ground response and available fault quantities |
| Load neutral interrupted, source bond intact | How do the single-phase loads return current? | Load-star-point and branch-voltage redistribution |
| Another ground source connected | Does it provide a represented return path? | Topology, impedance and protection location |
| No defined conductive reference in the modeled region | Which capacitive or instrument paths remain? | Voltage reference and sensitivity to those paths |
Recalculate the relevant fault loop
For the specified topology, trace the path from source to the fault and back. Include transformer sequence behaviour, grounding impedance and the actual conductor network. A fault current calculated for the intact bond cannot be reused after its return path changes. [2]
The SEL grounding study explains that a system can remain energized while losing its effective grounding source. It also describes capacitance and voltage observations in ungrounded conditions. Those application examples do not establish a universal LV bonding scheme or continued-operation permission. [2]
Check what the protection can see
Compare expected currents and voltages with the measurement locations and the actual scheme coverage. A smaller ground-fault current can weaken a current-based observation even while phase-to-ground voltage stress changes. A voltage indication may reveal a system condition without locating the failed bond uniquely. [2]
Retain switching state, other connected sources and instrument reference in the analysis. An apparent displacement could involve a reference-path change or measurement impairment; it requires independent evidence rather than automatic assignment to one bond.
Document the remaining fault-return routes, phase-to-earth voltage stress and protection sensitivity after the bond failure. Submit that circuit-specific result with the installation requirements and approval responsibilities, so the engineering review can address the actual grounding arrangement.
References
- B. Kasztenny, M. Thompson and N. Fischer, Schweitzer Engineering Laboratories, Fundamentals of Short-Circuit Protection for Transformers, 2012 revision.
- D. De Ronde, R. VanHatten and A. Wade, Schweitzer Engineering Laboratories, Loss of Effective System Grounding — Best Practices, Protection Challenges, and Solutions, 2015.