Each unit in a bank of single-phase transformers has its own DC current path and thermal history. Allocate the signed neutral-current sum to those paths, then assess the local exposure of each transformer. [1]
Regional GIC models need explicit transformer and grounding connections. The subsequent equipment assessment must retain the current allocation relevant to each magnetic circuit, rather than replacing it with a convenient bank average. [2]

Declare the sign and path of each current
For a common neutral with a consistent orientation, IN = IA + IB + IC. This is a signed summation, not a rule that each current equals IN/3. If several neutrals or common winding sections exist, use their actual nodes and section currents.
For an illustrative bank of equal-turn single-phase units, IA = 8 A, IB = 3 A and IC = 1 A produce IN = 12 A. Assigning 4 A to every phase would understate phase A’s current by half and overstate phase C’s by a factor of four. These assumed numbers demonstrate allocation error only.
Build a phase-specific exposure map
| Phase record | Required input | Result to retain |
|---|---|---|
| Electrical path | Line, winding and grounding connections | Signed DC current for the relevant section |
| Magnetic excitation | Turns and winding orientation | Signed sum of turn-current products |
| AC operating condition | Voltage, load and waveform | Comparable baseline for that phase |
| Local thermal response | Construction, initial temperature and duration | Phase-specific governing location and history |
| Measurement support | Independent channels and uncertainty | Whether the allocation is measured or inferred |
Equal current does not guarantee equal ampere-turns when winding sections or turns differ. For autotransformer arrangements, a high-voltage terminal current and a common-section current can contribute differently to the signed magnetic input. Preserve those contributions before comparing phases.
Check why the distribution became unequal
Inspect the represented branch DC resistances, parallel circuits and available grounding paths. A changed phase configuration can be a topology issue rather than a resistance tolerance. Verify that the network model did not force equality through a merged node that removes the physical distinction.
One neutral monitor cannot uniquely recover three unknown phase currents. Additional measurements or a supported network calculation are needed. If the allocation remains uncertain, assess credible phase distributions consistent with the observed sum instead of presenting the equal division as measured fact.
A single-phase bank and a three-phase unit also have different magnetic coupling. Do not transfer a bank’s independent-unit response directly into a common-core model without representing the shared flux paths.
Carry the phase allocation into local-loss and thermal calculations and identify the governing unit. Preserve its current and cooling history throughout the assessment.
References
- NERC, Transformer Thermal Impact Assessment White Paper, Project 2013-03 Geomagnetic Disturbance Mitigation, October 2017.
- R. L. Bailey and coauthors, Modelling geomagnetically induced currents in midlatitude Central Europe using a thin-sheet approach, Annales Geophysicae 35, 2017. DOI: 10.5194/angeo-35-751-2017.