Transformer impedance can vary with tap position because the effective turns and leakage geometry seen by the study change. A single nameplate percent-Z value may represent a principal tap or specified test position only. If fault current, parallel loading or regulation is sensitive to tap position, request the impedance data or guaranteed limits at the relevant extreme taps and use the actual operating tap for each scenario.

Separate physical variation from base conversion
A reported percent impedance can change because the winding's effective leakage parameters change, because the voltage/power base changes, or both. Ask whether each tap value is quoted on its own tapping quantities or on one common reference base. Converting every value to a common base exposes the difference. Scaling a principal-tap percentage by voltage alone does not establish the actual leakage impedance at another tap. The manufacturer's tap-dependent data are particularly important where regulating-winding placement affects the leakage field.
Select taps from the operating cases, not convenience
Include principal and relevant extreme taps, but also any intermediate operating point identified by the control philosophy or loading schedule. Maximum fault current is not automatically associated with the tap having the largest printed voltage. The available secondary voltage, winding current limit and impedance all participate. For parallel banks, compare each unit's ratio and impedance at its actual tap combination. Two position indicators showing the same number do not guarantee equal ratios when tap schedules or principal positions differ.
Keep the tap table connected to the study model
The data handover should include tap number, turns or voltage ratio, allowed MVA/current, impedance basis and any unavailable operating positions. Use explicit labels for measured, guaranteed and interpolated values. Interpolation may be suitable for a screening model but should not silently become a guaranteed test result. Reissue affected fault and sharing cases when the manufacturer revises the tap design. A corrected tap schedule can change the study even when the transformer headline rating and connection symbol remain the same.
Technical reference framework
[1] IEC 60076-1:2011 — Power transformers, General.
[2] IEC 60076-5:2006 — Ability to withstand short circuit.
[3] IEC 60076-8:1997 — Application guide.