Before transformers are paralleled, confirm ratio and tap compatibility, vector group and phase displacement, polarity/phase sequence, frequency, impedance magnitude and X/R, grounding, ratings, cable paths and protection philosophy. Similar nameplates are not enough. The final check should use the actual operating tap and measured or guaranteed impedance data for the intended bus configuration.

Separate voltage compatibility from load-sharing capability
Matching no-load secondary voltage and phase displacement is the first issue; acceptable current sharing under load is a separate one. Two transformers can pass a ratio comparison yet divide load poorly because their total impedances differ. Conversely, equal percent impedance does not correct an incompatible phase displacement. Use a comparison sheet that records ratio at the proposed taps, phasor relationship, frequency and impedance on an agreed basis. Do not collapse these independent checks into a single statement that the nameplates match.
Model the common bus rather than isolated transformer terminals
Include the cable or busduct from each transformer to the common point, the upstream source arrangement and the grounding connections. A compatibility calculation that stops at the transformer terminals can miss unequal cable drops or an additional zero-sequence path introduced by the bus tie. Determine each unit's current and reactive contribution at the expected maximum and minimum loads. Also check the single-unit state, where the remaining transformer may have a different loading or protection constraint.
Turn the engineering result into acceptance criteria
The approved checklist should distinguish document evidence from measurements and functional tests required during commissioning. Identify responsible parties for phase verification, control interlocks, protection groups and confirmation of the permitted bus states. Outstanding information should remain visibly open rather than becoming an assumed pass. The final authorization belongs to the installation's engineering and operating process; a generic checklist does not constitute permission to connect sources or perform live switching.
Technical reference framework
[1] IEC 60076-8:1997 — Application guide.
[2] Schneider Electric — Substation including generators and parallel operation of transformers.