After a cable-transformer fuse operates, the remaining phase connections, capacitance and magnetic state form the circuit behind any recorded overvoltage. Reconstruct that topology and source-input history to test the ferroresonance explanation.
Ferracci includes single-fuse and open-phase configurations among diagnostic cases. The event still needs reconstruction because fault transients, intermittent arcing and measurement effects can produce other abnormal traces. [1]

Build the complete topology timeline
| Interval | Connection evidence | State to retain |
|---|---|---|
| Before the initiating fault | Actual phases, load and grounding | Magnetic and capacitor baseline |
| Fault before interruption | Fault path and conducting devices | Changing flux and stored charge |
| Effective fuse interruption | Which phase ceased conducting and when | State entering the altered circuit |
| Post-fuse interval | Remaining phases, branches and protection state | Supply path and subsequent response |
A command or alarm timestamp may not identify the effective electrical interruption. Retain its uncertainty and compare it with current cessation where the record permits. [1]
Check whether further devices operated after the first fuse. A later three-phase isolation creates a different interval and should not be blended into one supposedly steady post-fuse circuit.
Carry inherited charge and magnetic history
The post-fuse network begins with states created during the preceding fault. Resetting every capacitor and core to zero at fuse interruption can produce a different response from the actual event. [1]
Where those states are uncertain, construct credible ranges from the preceding connection and waveform evidence. Do not choose the one initial condition that reproduces a desired abnormal trace and call it measured history.
Compare the competing explanations
A sustained nonlinear response needs a continuing supply path and sufficient persistence beyond the initial fault transient. Identify that path through the remaining phases or capacitive coupling rather than assuming an open phase is completely disconnected. [2]
Compare onset, frequency content, phase relationships and recovery against intermittent fault behavior, switching transients and sensor limitations. Harmonic distortion is shared by several mechanisms and cannot uniquely identify ferroresonance.
Use numerical models with the reconstructed topology sequence and retain failed predictions. If the candidate model cannot reproduce an independently established timing or phase relationship, that mismatch needs explanation.
Tie the diagnosis to the supported topology timeline and effective interruption record. Obtain missing phase-status or source-path evidence needed to establish the mechanism.
References
- P. Ferracci, Schneider Electric, Ferroresonance, Cahier Technique No. 190, March 1998.
- D. A. N. Jacobson, Examples of Ferroresonance in a High Voltage Power System, IEEE PES General Meeting, 2003. DOI: 10.1109/PES.2003.1270499.